Q1 2020 – Filed Preliminary Public Involvement Program Plan with NYSDPS - CONFIRMED
Late Q1 2021 – File Final Public Involvement Program Plan with NYSDPS - CONFIRMED
Q2 2020 – Public Informational Open House Meeting Held - CONFIRMED
Q2/Q3 2020 – Filed Preliminary Scoping Statement - CONFIRMED
Q4 2020 – Public Informational Open House Meeting Held - CONFIRMED
Q1 2021 – Filed Stipulations - CONFIRMED
Q2 2021 – Public Informational Open House Meeting Held (April) - CONFIRMED
Q4 2021 - Virtual Public Informational Open House Meeting Held (November) - CONFIRMED
Q4 2021 - In-Person Public Informational Open House Meeting Held (November) - CONFIRMED
Q1 2022 - File 94c application
Q1 2023 – ORES decision on 94c application
Q1 2024 – Commercial Operations